When to use it

Hiring a contractor to build a whole new house, with the contractor supplying all materials and labour.

What is in this document

  • Drawings, material list and BOQ attached as part of the contract
  • Payment only for inspected work stages, with a 7-stage schedule
  • Daily penalty for late handover, and retention
  • Right to terminate and hire another contractor if work stops or is abandoned
  • Warranty periods for structure and general work after handover

Sections in the document

  1. Scope of work
  2. Contract price
  3. Payment by work stage
  4. Construction period and progress reports
  5. Materials and quality
  6. Additions, omissions and changes
  7. Inspection of work
  8. Penalty for late handover
  9. Retention
  10. Warranty against defects
  11. Termination
  12. Safety and damage to others
  13. Permits and subcontracting
  14. Contact and notices
  15. Dispute resolution
  16. Attachment: work stage and payment schedule

How to use it

  1. Download the Word file and fill in every blank. Delete any option you do not use.
  2. Attach the drawings, material list, BOQ and payment schedule, and have both sides initial every page.
  3. Have a lawyer review it, especially for high-value work.
  4. Sign before two witnesses, attach the full stamp duty, and keep one copy each.

Sample text from the document

Clause 1 Scope of work

The Owner agrees to hire, and the Contractor agrees to build, a house ........................................ of .......... storeys on land title deed no. .................... located at ................................................................................. The Contractor supplies all materials, labour, tools and equipment and completes the work in full according to the attachments, which form part of this contract, as follows:

If the attachments conflict, this contract prevails, followed by the construction drawings, the material list and the BOQ in that order, or as the parties agree in writing.

Frequently asked questions

How is a house construction contract different from a labour-only contract?

In a house construction contract the contractor supplies both materials and labour, and one price covers all the work in the drawings. In a labour-only contract the owner buys the materials and hires only the labour, so the contract needs extra clauses on delivering and looking after materials.

What documents should be attached to the contract?

The construction drawings, material list, bill of quantities and prices (BOQ), work plan, payment schedule and the list of work not included in the price, plus copies of each party's ID card or company certificate.