Residential construction

Labour-only vs turnkey

TopicLabour onlyTurnkey
Who buys materialsThe ownerThe contractor
Owner's timeA lot: ordering and timing deliveriesLittle: inspect each stage
Waste or damaged materialsOwner pays, unless the contract says otherwiseContractor bears it
Delays from late materialsOwner's responsibility; the contractor may extendContractor's responsibility
Best forSmall jobs, extensions, painting, tilingA whole house or structural work

How much of a house build is labour?

Across 21 house BOQs, labour is 29.5%–32.6% of the work cost before overhead and VAT, with a median of 31.6%. About two thirds is materials.

For example, Twin Cube, a 1 storey 2-bedroom home of 39 sq.m., has 558,005 THB of materials and 258,110 THB of labour.

The labour share varies a lot by category (Twin Cube):

CategoryLabour share of that category
Wall finishes52%
Floors and tiles42%
Painting41%
Piles, footings and ground beams39%
Railings and counters23%
Sanitary ware19%
Doors and windows18%

Labour-heavy work such as plastering, tiling and painting suits labour-only hiring, because you choose the material grade. For doors, windows and sanitary ware most of the money is in the product.

When labour-only pays off, and when it does not

  • Pays off: small jobs where you can buy everything at once, you can visit the site, or your supplier beats the contractor's prices.
  • Does not: a whole house or structural work, where steel, concrete and piles must arrive on time. Late materials leave the crew waiting, and the delay is yours.

6 clauses a labour-only contract needs

  1. Who supplies what, with a list of owner-supplied materials; tools belong to the contractor.
  2. Advance material requests, with the number of days' notice.
  3. A signed record of every delivery.
  4. Liability for lost or damaged materials beyond normal waste.
  5. Labour paid by inspected work, not by date, and never ahead of real progress.
  6. Late penalties, workmanship retention and the right to terminate after a long stoppage.

All six are in our labour-only contract, with a material receipt form attached.

If you would rather not buy materials yourself

Use the turnkey contract and ask the contractor to attach a BOQ that names the brand and grade of every item. You keep the same control over quality without being on site every day. See fully itemised BOQs in our free house plans.

Planning to build? See every item before you decide.

Send your location, plans or photos and we will come back with an initial scope of work.

Frequently asked questions

Do I need a contract for labour-only work?

Yes. It must cover liability for materials, which is where most disputes start.

What share of a house build is labour?

Across our 21 BOQs, labour is 29.5%–32.6% of the work cost before overhead and VAT.

Can I edit the contract?

Yes. It comes as an editable Word file and a PDF for printing.