A completed private residence built for an international homeowner

Language: two languages, and say which one wins

Thai courts work in Thai. An English-only contract is valid, but in a dispute it must be translated, and the translation may not say what you thought you agreed. Sign a Thai and English contract from the start, state which version prevails if they differ, and have a lawyer or a translator you trust compare both before you sign.

Scope: always attach drawings and a BOQ

"Build one house for X baht" is how extra charges start. The contract should refer to the construction drawings and a BOQ (bill of quantities) that names the material, brand and size of every item, with a clear list of what is not included. You can open full BOQs in our free house plans.

Payments: pay for finished work, not for dates

Our BOQs split the price into 7 stages, each tied to inspected work. Here is Hip Garden as an example.

StageShareAmount (THB)
110%167,659
215%251,489
320%335,319
420%335,319
515%251,489
615%251,489
75%83,830

Stage 1 is paid on signing, the middle stages follow the structure, roof, walls, systems and finishes, and the last 5% is paid at handover. Never pay ahead of the work you can see, and sign an inspection form for each stage. More in How to split construction payments.

Sending the money

  • Pay only into an account in the name of the contractor who signed the contract, never a third person's private account.
  • If you bring in foreign currency, keep the bank's record of every transfer. You may need it later to show where the money came from, or to send funds back out.
  • Ask whether the price includes 7% VAT and whether the contractor issues tax invoices.

Warranty

The Civil and Commercial Code's rules on hire of work make the contractor liable for defects that appear within 1 year of delivery, and within 5 years for structures on the ground other than wooden buildings. A good contract states the warranty directly. Our BOQs give 5 years on structure and 1 year on general work from handover.

Changes and termination

Every change should be in writing, with its price and extra time, signed by both sides before work starts. The contract should also say how long the builder can stop work before you may terminate. Our free construction contract covers these points. The download is in Thai, as it is written for Thai law; for our own clients we prepare a two-language version.

This article is general information, checked against public sources in November 2026. Laws change and every case is different. Before you sign or pay anything large, have a Thai lawyer review your own documents.

Planning to build? See every item before you decide.

Send your location, plans or photos and we will come back with an initial scope of work.

Frequently asked questions

Can my construction contract be in English only?

It can, but in a dispute it must be translated into Thai for the court. A two-language contract that says which version prevails is safer.

How much should I pay up front?

There is no fixed number. Our BOQs take 10% on signing. The rule is never to pay more than the value of work actually done.

What warranty does Thai law give on construction?

Under the Civil and Commercial Code the contractor is liable for defects appearing within 1 year, and 5 years for structures on the ground other than wooden buildings.