How the bank pays

A construction loan is paid in stages as the work progresses, usually after the bank inspects the site.

House documents banks usually ask for

  • Building permit
  • Drawings
  • A construction contract with payments tied to progress
  • A BOQ listing materials and prices
  • Land title

Line up the stages

StageShare
110%
215%
320%
420%
515%
615%
75%

The bank usually does not pay the signing stage, because there is no work to inspect yet, so keep your own cash for it. Show the contractor's schedule to the bank before you sign.

This article is general information, checked against public sources in November 2026. Laws change and every case is different. Before you sign or pay anything large, have a Thai lawyer review your own documents.

Planning to build? See every item before you decide.

Send your location, plans or photos and we will come back with an initial scope of work.

Frequently asked questions

When does the bank pay the contractor?

In stages as the work progresses, usually after a site inspection for each stage.