Residential project construction

Remember the number 10

The Land Development Act B.E. 2543 (2000) defines land allotment as selling land divided into 10 or more plots, and forbids it without a licence from the Land Allotment Committee. Doing it without one is a criminal offence with prison and fines.

Splitting into 9 plots several times doesn't get around it. The law counts divisions of the same land within 3 years, and the land officer can require an allotment application if a subdivision looks like one.

The order to follow

  1. Check zoning. What does the town plan allow on this land? Ask the provincial Public Works and Town Planning office or the local authority.
  2. Check the land. Is it a full title deed (Chanote)? Is there legal road access? Any mortgage or servitude on it?
  3. Design the layout to the province's allotment rules: minimum plot size, road width, drainage, common areas. Each province has its own.
  4. Apply for the allotment licence at the provincial Land Office, with the layout, utility drawings and a guarantee for building the utilities.
  5. Get building permits for the houses from the local authority under the Building Control Act.
  6. Use the standard sale contract set by the Central Land Allotment Committee.

When an EIA is needed

Project typeEIA required when
Residential land allotment500 plots or more, or more than 100 rai
Residential building / condominium80 units or more, or 4,000 sq.m. or more of usable area

Most first projects are well below this. Some areas, such as parts of the coast, have stricter environmental protection rules, so check locally.

Fewer than 10 plots

No allotment licence, but zoning, building permits and taxes on sale still apply. It is faster and lighter. The downside: there is no housing estate juristic person, and rights over the internal road must be set up properly, or buyers will have access problems later.

A builder's tip

Permits take time, and your land cost sits there while you wait. Use that time to finish the BOQ for each house type, so you can start building and set prices the day the licence arrives. See sample figures in Costing a 10-house project.

An amendment to the allotment law is in progress, so numbers and steps may change. Always check with the provincial Land Office before you apply.

This article is general information, checked against public sources in November 2026. Laws change and every case is different. Before you sign or pay anything large, have a Thai lawyer review your own documents.

Planning to build? See every item before you decide.

Send your location, plans or photos and we will come back with an initial scope of work.

Frequently asked questions

How many plots need a land allotment licence?

10 or more, under the Land Development Act B.E. 2543, counting divisions of the same land within 3 years.

Where do I apply?

At the provincial Land Office or its branch where the land is. The Provincial Land Allotment Committee decides.

When does a housing project need an EIA?

At 500 plots or more, or more than 100 rai. Residential buildings need one at 80 units or 4,000 sq.m. of usable area.