Hip Garden, a single-storey 3-bedroom house plan

BOQ stands for Bill of Quantities: a priced, line-by-line list of the work. If you are new to it, read What a BOQ is and how to read it first.

Price summary

PartTHB
Work, 96 lines (materials + labour)1,424,464
Overhead 10%142,446
VAT 7%109,684
Total1,676,594

That is 17,101 THB per sq.m. of the 98 sq.m. floor area. The plan is drawn for a 18x20 m plot.

Cost by category

Always compare categories first: when two quotations differ a lot, you see at once where.

CategoryTHBShare
1. Piles, footings and ground beams206,49914.5%
2. Reinforced concrete structure221,58315.6%
3. Roof236,10016.6%
4. Walls110,6527.8%
5. Wall finishes72,2705.1%
6. Floors and tiles143,29410.1%
7. Ceilings42,8093.0%
8. Painting49,1683.5%
9. Doors and windows136,7689.6%
10. Railings and counters18,7201.3%
11. Sanitary ware34,3202.4%
12. Electrical73,5605.2%
13. Plumbing and drainage78,7205.5%
Total work1,424,464100%

Every line of the BOQ

Each line gives the item, quantity, material rate and labour rate. Total = quantity × (material + labour).

1. Piles, footings and ground beams · 206,499 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Solid square piles, PC TIS 0.22x0.22 m length 6.0 m footing F1 (12 pcs x 6.0 m)72 m30613231,536
Solid square piles, PC TIS 0.18x0.18 m length 6.0 m footing F2 (4 pcs x 6.0 m)24 m2881209,792
Building setting-out, batter boards, level pegs1 lump sum1,8004,2006,000
Pile head cutting, debris removal16 pcs01802,880
Pile integrity test (Seismic test)16 pcs05408,640
Pile rig mobilisation/pile driver1 trips7,20007,200
Footing excavation41.66 cu.m02168,999
Coarse sand at the pit base, thickness 5 cm0.37 cu.m660180311
Lean concrete, thickness 5 cm0.37 cu.m2,5204801,110
Compacted backfill37.70 cu.m01445,429
Removal of surplus soil3.97 cu.m03001,191
Dewatering, footing pit shoring1 lump sum1,2002,4003,600
Termite protection under the building (pipe laying + chemical injection)107.80 sq.m783011,642
Concrete 240 ksc footing (F1 0.7x0.7x0.35 m 12 footings, F2 0.6x0.6x0.3 m 4 footings)2.49 cu.m2,9405408,665
Footing reinforcement SD40199.20 kg3277,769
Footing side formwork14.64 sq.m2162046,149
Concrete 240 ksc stumps 0.2x0.2 m (16 pcs)0.74 cu.m2,9405402,575
Stump reinforcement SD40 + stirrups SR24119.04 kg3274,643
Stump formwork14.88 sq.m2162046,250
Concrete 240 ksc ground beams (total length 68.6 m)5.49 cu.m2,94054019,105
Ground beam reinforcement SD40 + stirrups SR24768.32 kg32729,964
Ground beam formwork54.88 sq.m21620423,050

2. Reinforced concrete structure · 221,583 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Concrete 240 ksc columns 0.2x0.2 m above ground (16 pcs)2.20 cu.m2,9405407,656
Concrete 240 ksc roof beams (total length 68.6 m)5.49 cu.m2,94054019,105
Concrete 240 ksc porch roof beams (total length 7.8 m)0.47 cu.m2,9405401,636
Concrete 240 ksc carport roof beams (total length 12.6 m)0.76 cu.m2,9405402,645
Concrete 240 ksc topping on floor planks, thickness 5 cm4.90 cu.m2,94054017,052
Concrete 210 ksc slab on grade, thickness 10 cm3.34 cu.m2,94054011,623
Reinforcement, columns, beams, floors, stairs SD40 + stirrups SR241291.04 kg32750,351
Formwork, columns, beams, cast-in-place slab, stairs128.84 sq.m21620454,113
Flat-soffit precast floor planks98.04 sq.m3849647,059
Steel Wire mesh (topping + slab on grade)131.48 sq.m54148,941
Sand bedding for slab on grade, thickness 5 cm1.67 cu.m6601801,403

3. Roof · 236,100 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Structural steel roof frame, anti-rust paint 2 coats (hip roof over the house)1362.45 kg411272,210
Metal sheet roof 0.40 mm colour coated with screws and flashing (hip roof over the house)136.25 sq.m34810862,130
Roof insulation (hip roof over the house)136.25 sq.m843015,532
Fibre-cement fascia, charcoal paint (hip roof over the house)44.80 m36013222,042
Soffit, ventilated fibre-cement (hip roof over the house)25.44 sq.m33615612,516
Structural steel roof frame, anti-rust paint 2 coats (flat roof over the front porch)82.91 kg41124,394
Metal sheet roof 0.40 mm colour coated, slope 3 degrees (1:19) into the gutter with screws and flashing (flat roof over the front porch)9.21 sq.m3481084,200
Fibre-cement roof parapet, charcoal paint, height 40 cm with frame (flat roof over the front porch)8.60 m3601324,231
Close-fitted composite wood soffit with framing (flat roof over the front porch)9.20 sq.m7802409,384
Structural steel roof frame, anti-rust paint 2 coats (carport roof)189.26 kg411210,031
Metal sheet roof 0.40 mm colour coated, slope 3 degrees (1:19) into the gutter with screws and flashing (carport roof)21.03 sq.m3481089,590
Fibre-cement roof parapet, charcoal paint, height 30 cm with frame (carport roof)20 m3601329,840

4. Walls · 110,652 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Lightweight concrete block walls, thickness 7.5 cm164.44 sq.m30015674,985
Tie columns / lintel, RC around openings and wall ends114.20 m1329626,038
Projecting frame 2.60x2.35 m depth 40 cm thickness 20 cm galvanised steel frame, fibre-cement board cladding, charcoal paint (master bedroom window box)10.70 sq.m5403609,630

5. Wall finishes · 72,270 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Exterior wall plaster (including backing for stone/composite wood)90.18 sq.m7211416,773
Interior wall plaster238.69 sq.m6610240,100
Stone veneer on exterior walls15.27 sq.m66027614,293
Vertical composite wood battens, face 2 in with galvanised steel frame1.15 sq.m7442161,104

6. Floors and tiles · 143,294 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Bathroom wall tiles up to the ceiling + kitchen wall40.12 sq.m33622822,628
Sand-cement screed (interior floors)92.79 sq.m7810216,702
Sand-cement screed, sloped to the drain, no less than 1:200 (5 cm every 10 m) bathrooms no less than 1:100 (bathroom, balcony, porch, outdoor walkways)15.16 sq.m781022,729
Granito tiles 60x60 cm (F-1)75.24 sq.m28822838,824
Non-slip tiles, kitchen (F-2)25.11 sq.m48026418,682
Non-slip tiles, bathroom (F-3)7.60 sq.m5043006,110
Broom-finished concrete floor, laid to fall to the drain at no less than 1:200 car park/laundry yard (F-6)25.88 sq.m721686,211
Front entrance steps, RC tiled1 sets3,3601,8005,160
Skirting82.60 m1084212,390
Bathroom floor waterproofing + wall upstand 30 cm12.28 sq.m4561807,810
Granite door threshold/floor transition trims8.40 m5401806,048

7. Ceilings · 42,809 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Gypsum board ceiling 9 mm smooth-taped joints, framing (C-1)90.44 sq.m27615639,070
Moisture-resistant gypsum board ceiling 9 mm smooth-taped joints (C-2)7.60 sq.m3361563,739

8. Painting · 49,168 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Exterior paint, primer + finish 2 coats (white/charcoal)74.91 sq.m965411,236
Interior paint, primer + finish 2 coats198.57 sq.m664822,637
Ceiling paint123.48 sq.m544812,595
Smooth concrete finish on ground beams, exterior paint on the raised plinth band around the house (charcoal)18 sq.m96542,700

9. Doors and windows · 136,768 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
D4 hinged door HDF painted, standard leaf size 0.80x2.00 m with frame, hinges 3 pcs, lever handle with lock (0.80x2.10 m)4 sets3,1201,80019,680
D5 bathroom door UPVC standard leaf size 0.70x2.00 m with frame, lever handle (0.70x2.00 m)2 sets3,6001,0809,360
D6 black aluminium hinged door, frosted glass (kitchen / laundry yard) made to size with lever handle and lock (0.80x2.10 m)1 sets5,4001,0806,480
D7 black aluminium hinged door, clear glass (entrance from the parking) made to size with lever handle and lock (0.80x2.10 m)1 sets5,4001,0806,480
GL glass sliding door, black aluminium, tempered glass 6 mm (entrance) with handle and lock 1 set (2.20x2.40 m)5.28 sq.m3,36060020,909
W1 black aluminium window, sliding, glass 5 mm 6 sets (1.20x1.20 m)8.64 sq.m3,12054031,622
W2 black aluminium window, sliding (kitchen) 1 set (1.40x0.90 m)1.26 sq.m3,1205404,612
W3 black aluminium window, awning (bathroom) 2 sets (0.60x0.50 m)0.60 sq.m3,1205402,196
W4 tall black aluminium window, sliding + fixed 2 sets (2.20x2.20 m)9.68 sq.m3,12054035,429

10. Railings and counters · 18,720 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Masonry kitchen counter + granite top2.40 m6,0001,80018,720

11. Sanitary ware · 34,320 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Toilet with bidet spray2 sets3,8401,0809,840
Washbasin with tap2 sets3,3607208,160
Shower + valve + towel rail2 sets3,0006007,200
Floor drain grate4 sets4202402,640
Kitchen sink with tap1 sets5,4001,0806,480

12. Electrical · 73,560 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Lighting point with fitting LED and switch17 pts72048020,400
Double socket point with earth18 pts60042018,360
Air-conditioner point (cable + separate breaker)3 pts2,1609609,360
Water heater point (cable 6 sq.mm + RCD breaker)2 pts1,8008405,280
Electrical control panel Consumer unit + RCBO + earth rod1 sets7,8002,1609,960
Main cable from the meter + underground cable conduit1 lump sum4,8001,8006,600
Downlight points under the front porch eaves with fitting LED3 pts7204803,600

13. Plumbing and drainage · 78,720 THB

ItemQuantityMaterial/unitLabour/unitTotal (THB)
Fresh water point9 pts1,08072016,200
Waste water point/toilet7 pts96072011,760
Packaged septic tank 1600 litres1 sets16,8003,60020,400
Grease trap1 sets4,2009605,160
Water tank 1000 litres + automatic water pump1 sets22,8002,40025,200

Payment stages tied to finished work

StageWork completedShareTHB
1Contract signing10%167,659
2Piles, footings, stumps and ground beams complete15%251,489
3Columns, roof beams and ground floor complete20%335,319
4Roof frame, roofing and all walls complete20%335,319
5Plastering, electrical and plumbing runs, door and window frames and ceilings complete15%251,489
6Flooring, tiling, doors and windows, sanitary ware and painting complete15%251,489
7Inspection and handover5%83,830

Pay a stage only once its work is finished and inspected. More in Payment stages.

Not included in this price

  • Land, filling and site levelling
  • Building permit fees and the architectural and engineering drawings for the permit
  • Driveway and front yard outside the carport, fence, gate and landscaping
  • Air conditioners and water heaters (power points are provided as listed)
  • Wardrobes, loose furniture, curtains and decorative lights
  • Electricity and water meter applications with the electricity and waterworks authorities

Piles are priced as listed in group 1. Actual pile length follows the soil test, at the per-metre rate in the table Additions or omissions from the plan are priced at the unit rates in the table 5-year structural warranty and 1-year general warranty from handover

Every single-storey plan in our library

PlanRoomsFloor areaTotal (THB)THB/sq.m.
Twin Cube2 bed, 1 bath39 sq.m.960,56724,411
Wood Slat One2 bed, 1 bath38 sq.m.962,76525,230
Gable Nest2 bed, 1 bath37 sq.m.964,24326,389
Breeze Loft2 bed, 1 bath37 sq.m.968,56526,464
Mini Box2 bed, 1 bath49 sq.m.1,082,16322,085
White Court3 bed, 2 bath97 sq.m.1,646,82416,957
Hip Garden3 bed, 2 bath98 sq.m.1,676,59417,101
Tudor Mini3 bed, 2 bath95 sq.m.1,711,78217,966
Wood Wing3 bed, 2 bath98 sq.m.1,971,07120,162

Open any of them in our free house plans, tap "Price" and choose "Every line".

How to use this example

Set up the Excel BOQ template with the same categories, send it to every contractor, and attach the agreed BOQ to the house construction contract. It works for one- and two-storey homes.

Planning to build? See every item before you decide.

Send your location, plans or photos and we will come back with an initial scope of work.

Frequently asked questions

How many lines does a single-storey house BOQ have?

Our single-storey plans have 86–102 lines each; this one has 96.

Which category costs the most in a single-storey house?

Here it is roof, at 16.6% of the work. A single-storey roof covers the whole floor area, so the roof share is high.

Can I use this price for my own plot?

Use it as a budget frame. Pile length is set by the soil test, and work outside the plan such as land filling, fences and driveways is not included.