A contractor has abandoned the job when they stop work without good reason, cannot be reached, or work so slowly that the deadline clearly cannot be met, after being paid. In most cases this is a civil breach of a contract for work. What you need is evidence that shows how much you overpaid and how much you lost.
-
Collect evidence now, before touching the site
Take dated photos and video of every part of the site. Gather the contract, drawings, BOQ, every bank transfer, receipts and all chat messages. If materials are on site, photograph and count them. These records show how far the work had progressed on the day the contractor stopped.
-
Contact them, and keep it in writing
Call, and also send a message asking why work has stopped, so there is a record you can refer back to. Sometimes the contractor has a real problem and can return. If you agree on that, make a new written agreement with the return date and work plan.
-
Send a written notice to resume work
Send a notice by registered mail with return receipt to the address in the contract. State the breach and give a reasonable deadline to return. This step matters, because in many cases a contract can only be terminated after notice to perform within a reasonable time (section 387).
Free documentNotice to resume work
The contractor has stopped work, cannot be reached or is very late, and you want to warn them in writing to return.
-
Terminate the contract in writing
If the deadline passes and the contractor is still silent, send a termination letter and arrange a joint count of the work done and materials on site. If the work is so slow that it clearly cannot finish on time, the law also lets the owner terminate without waiting for the handover date (section 593).
Free documentTermination letter
You have sent a warning, the contractor has not returned, and you have decided to bring in someone new.
-
Value the work done before hiring a new contractor
Have the new contractor or an expert assess the value of the work already done and which parts must be redone, then compare it with what you have paid. The difference is your overpayment. What the new contractor charges above the unpaid balance of the original contract is the loss you can claim.
Use the stage inspection form to record the work done in front of witnesses -
Claim your money, mediate or sue
Send a written demand for the overpayment and your losses. If it is not paid, ask a lawyer about mediation or a civil claim. Smaller claims may qualify as a consumer case or a small claim, depending on the facts, which is simpler than an ordinary case. A lawyer can tell you which applies.
Prevention is better than chasing your money
Most contractors who walk away show warning signs first: a large advance, pressure to pay before work is done, a one-line lump-sum quotation, or refusing a late penalty in the contract. Use the contractor hiring checklist and a complete construction contract from the start, and split payments so they never run ahead of the work. Then even if a contractor disappears, your loss is only a small difference.
Need a contractor to finish the job?
We take on work left unfinished by another contractor. Send us site photos, the drawings and the original BOQ. We will tell you what needs to be finished and what needs fixing, with a price for each item, before you decide.
Planning to build? See every item before you decide.
Send your location, plans or photos and we will come back with an initial scope of work.
Frequently asked questions
Can I sue a contractor who abandoned the job?
Yes, for breach of a contract for work, to recover payments above the value of the work, the extra cost of hiring a new contractor, penalties and other losses under the contract and the law. Ask a lawyer to assess your evidence.
How many days of stopped work before I can terminate?
It depends on the contract. If it sets a number of days, use that. If not, send a notice to resume within a reasonable time before terminating. If the delay makes it clear the work cannot finish on time, the owner may terminate before the handover date.
Can I hire a new contractor straight away?
First terminate in writing and record the state of the work with witnesses. Otherwise the original contractor may dispute the value of the work done, and your loss will be hard to prove.