The part with real numbers: building the houses
This table simply multiplies each BOQ price by 10, with no volume discount applied. Prices include 10% overhead and 7% VAT.
| Plan | Storeys / bedrooms | sq.m. | Per house (THB) | 10 houses (THB) |
|---|---|---|---|---|
| Hip Garden | 1 / 3 | 98 | 1,676,594 | 16,765,940 |
| Family Four | 2 / 4 | 98 | 1,740,788 | 17,407,880 |
| Slim Two | 2 / 3 | 99 | 1,942,546 | 19,425,460 |
| Cube Duo | 2 / 3 | 149 | 2,646,167 | 26,461,670 |
Where the money goes
Hip Garden by work section, before overhead and VAT.
| Work section | Per house (THB) | 10 houses (THB) |
|---|---|---|
| Piles, footings and ground beams | 206,499 | 2,064,990 |
| Reinforced concrete structure | 221,583 | 2,215,830 |
| Roof | 236,100 | 2,361,000 |
| Walls | 110,652 | 1,106,520 |
| Wall finishes | 72,270 | 722,700 |
| Floors and tiles | 143,294 | 1,432,940 |
| Ceilings | 42,809 | 428,090 |
| Painting | 49,168 | 491,680 |
| Doors and windows | 136,768 | 1,367,680 |
| Railings and counters | 18,720 | 187,200 |
| Sanitary ware | 34,320 | 343,200 |
| Electrical system | 73,560 | 735,600 |
| Plumbing and drainage | 78,720 | 787,200 |
This shows when you'll need the cash. Piles, structure and roof take close to half of it in the first half of the job.
The part where you need your own numbers
We don't give figures here, because they depend on your land and province. But every line belongs in your cost sheet.
| Cost line | Who to ask |
|---|---|
| Land, plus transfer fees when you buy | The Land Office |
| Filling and levelling | A local earthworks contractor, after a level survey |
| Internal roads, drainage, electricity and water | Your design engineer and the utility providers |
| Design, allotment and building permits, utility guarantee | Your designer and the provincial Land Office |
| Fence, signage, entrance, common areas | Your contractor (ask for a separate BOQ) |
| Marketing, show house, sales commission | Your own marketing plan |
| Loan interest during construction and sales | Your bank |
| Taxes and fees on transfer to buyers, corporate income tax | Your accountant |
| Contingency | Your call, based on the risk you can carry |
Setting the sale price
- Add up every line above for the whole project.
- Divide by the number of houses. If plots differ, share the land cost by plot size.
- Add the profit you want, then compare with nearby projects that actually sold.
- If your price is above the market, change the house plan or the specification. Don't cut the contingency.
One thing we'd stress is time. Every month that sales run behind plan, interest eats profit. Work out two cases, sold on plan and sold in twice the time, and see if you can still carry it.
For a rental building
It works the same way, per room. For example Row Five has 5 rooms and costs 2,490,809 THB to build, or 498,162 THB per room. More in Rental building construction cost.
Where we can help
Send your drawings or pick from our plans. We prepare a BOQ per house and for the whole project, with a payment plan by phase, so you have a construction figure you can take to the bank.
Planning to build? See every item before you decide.
Send your location, plans or photos and we will come back with an initial scope of work.
Frequently asked questions
How much does it cost to build 10 houses?
It depends on the plan. From our BOQs, 10 × Hip Garden (98 sq.m.) comes to 16,765,940 THB including overhead and VAT, excluding land and infrastructure.
What does a project cost besides construction?
Land, filling, infrastructure, design and permits, common areas, marketing, interest, taxes and transfer fees, and a contingency.
Is it cheaper to build several houses at once?
Bulk buying and continuous work generally help, but how much depends on real quotations for that project.